Beaver College of Health Sciences - Week of 4/24/17 - 4/28/17

Here's a feel for the finished product. (Mock up being used in construction.)
Monday, May 1, 2017 - 2:45pm

This week we've been able to get a feel for the building's scope and size.  It's visible from the stop light at 321 and Deerfield Road intersection.

Other parts of the building are beginning to take shape and are visible now that the privacy/shade fencing has been removed from the chain link fencing surrounding the site.

 

This week's accomplishments include:

Mockup construction nearing completion.

Steel Erection continuing

Slab on grade concerte pour on west side completed (areas A & C)

Fireproofing underway

Decking continues

Curb and gutter install

 

exterior BCHS

Curbing