Beaver College of Health Sciences - Week of 1/9/17-1/13/17

Cold weather curing of concrete.
Wednesday, January 18, 2017 - 10:57am

Weekly Summary: 1/9/17 - 1/13/17

After a weekend of temps that never climbed out of the teens, construction workers finally got a break on Thursday, January 12th when Boone reached an incredible high of 64 degrees!  But the cold weather earlier in the week didn't prevent intrepid construction workers from setting up tents and pouring concrete, taking "cold weather curing" precautions. (See photo.)

Progress this week included:

Elevator wall pours completed.

Concrete wall pours nearing completion.

Damp Proofing and waterproofing continue as walls cure.

Backfill/compaction at poured walls and piers continues.

Grease interceptor tanks delivered.

Sanitary sewer line test completed.

 

Backfill compaction

Concrete pumper filling walls.

Submit a Work Request

How may we help you?

I need..

Contact

Physical Plant
265 Dale Street
PO Box 32105
Boone, NC 28608-2105
Phone: 828.262.3190

Fax: 828.262.4017

QEP Global Learning


Advanced